Modular classes may not be ready for school!

0

The COM had announced at the start of the year the establishment of fourteen additional classes for the start of the school year in September 2019 to unclog the school complex while awaiting the construction of the new college 900. 

The call for tenders having been published on May 2 and extended until June 11, it seems unlikely that the classes will be operational for September. 

The duration of the works is estimated at sixteen weeks, i.e. eight weeks of preparation (two weeks more than the duration initially indicated) and eight weeks of work.

Each class will be equipped with two air conditioners, six windows with roller shutters and mosquito nets. 

(Source: www.soualigapost.com)