Merchants from the Royal Marina met with the community-appointed architect last week during a working meeting. It related to the presentation of the “temporary quay work project”.
“These works will initially consist of removing the planks from the deck as well as the beams in poor condition.
Then by replacing the joists and installing marine plywood over the entire deck, ”reports Yann Lecam, the president of the Citizen Economic Association (AEC). And to specify that "the planks of marine plywood will be covered with a synthetic turf type coating." It is also planned that flower boxes will be placed along the quay.
The work carried out by the agents of the technical service of the community, should start this week.
Source: www.soualigapost.com)