Culture: Concordia's cultural shelter delivered at the end of 2022

0

The renovation and transformation project of the media library should be completed in the last quarter of 2022.

During the territorial council of March 31, mainly devoted to budgetary orientations, Jean-Sébastien Roca, AFD, presented the next four major investment projects of the COM, including that of a Concordia cultural shelter, instead. and place of the old media library.

The new building, called the Concordia Cultural Shelter, will be constructed from the concrete structure of the media library. It will only include two levels (against three before), and the large windows, generating heat and too fragile will be removed. “It will be more minimalist and more solid, earthquake-resistant and anticyclonic,” said the AFD technician.

The basement will therefore house a cyclone shelter and a medical shelter which will be made available to the hospital. The amphitheater, built on two levels, will be rehabilitated. The first floor will be devoted to welcoming users, with a snack bar, the kitchens of which can be used in the event of a cyclone, then rooms dedicated to the media library / games library, a virtual museum, music.

"We have received the validation of the prefecture for this development" announced Jean-Sébastien Roca, who explains that in the interest of the COM and the population, the architectural firm commissioned initially to carry out a diagnosis of the building and a security project, will be the prime contractor for the rest of the work. “After discussing it with the legality check in the presence of the President and the entire COM team, the prefect authorized us to continue with this company since it was for the benefit of the COM, which makes us save considerable time: seven months. ".

The schedule announced is as follows: validation of the project at the end of May, filing of the permit in July, start of demolition and securing in summer 2021, start of work in the last quarter of 2021 then delivery in the last quarter of 2022.

The estimated budget amounts to 3 euros, including 940 for demolition and cleaning, 000 for securing and protection of the building, and 660 euros for interior refurbishment work. The State (FEI) finances 000 million euros, React EU Vert 540 euros and the COM pays 000 euros from its own funds.

(More details on www.soualigapost.com)