The Collectivity of Saint-Martin informs its citizens of the resumption of asbestos removal works on the buildings of the Collectivity.
Thus, the work is carried out as follows:
Nina Duverly School:
• Asbestos removal work carried out from June 17 to 28, 2019, for the classrooms on the ground floor.
• Asbestos removal work from June 25 to July 03, for the director's office
• Fallback operation linked to asbestos removal, planned from June 28 to July 11
Building rue de la Liberté in Marigot (former Legal Center):
v Installation of the scaffolding on June 24 and 25
• Preparation of asbestos removal work until July 03
• Asbestos removal work the first half of July
Note that asbestos removal work is subject to special monitoring:
• The work is carried out in sealed areas, placed under vacuum, the exhaust air being filtered by a double filtration extractor system
• Air analysis in the work area
• Air analysis near work areas
• Analysis of exhaust air from extractors
Following the asbestos removal work, the deconstruction work on these two buildings badly damaged by Irma will be carried out. Specific protection measures will be implemented to reduce nuisance:
• Misting to reduce dust
• Par-rubble and mechanical protection to channel rubble
The Collectivity of Saint-Martin would like to apologize for the inconvenience caused to the neighborhood during the works period.