Repair of a portion of the Grand-Case road: all night shifts mobilized to respect the schedule

0

The rehabilitation work of the water and sanitation network, which has been under way for several months in Grand-Case, must logically end this Saturday, October 10 at 6 a.m. The many workers present at night are doing it!

Since the start of the week, the EEASM has been carrying out the final stage, which is the repair of the road on the affected portion, over approximately 450 meters.

The works, planned over 5 days, are carried out strictly at night, from 20 p.m. to 6 a.m., and require the installation of an alternating circulation system.

As a reminder, they began on Sunday October 5 to end this Saturday October 10, 2020 at 6 a.m. if the schedule is respected.

The weekend could allow in case of delay related to the conditions to finish the work while minimizing the impact for the users.

The affected part of the roadway is rehabilitated with a concrete coating and upgraded. This solution was favored since in terms of planning, the asphalt paving campaign deployed by the Collectivity will treat this section of the RN7 in its entirety before the end of the year.

On Wednesday evening, the president, Daniel Gibbs went to Grand-Case to check the progress of the work. One thing is certain, the many workers in charge of the site are not idle. A precision that deserves to be underlined. _AF